Landmark Transilvania Bridge completed in Satu Mare

Business Forum
Strabag Romania in collaboration with the Satu Mare Municipality Town Hall announced the official handover of the new cable-stayed Transilvania Bridge over the Someș River.

The 644-meter-long bridge will stand as the longest cable-stayed bridge in the country and is the biggest infrastructure project completed in Satu Mare in the last four decades.

The construction, valued at approximately RON 200 million lei (€40 million), commenced in May 2020 and comes with a 15-year warranty period.

The bridge is supported by two 73-meter-high pylons and 56 high-strength steel cables. The cable-stayed assembly supporting the bridge alone weighs 227 tons and is engineered to bear a load exceeding 12,000 tons.

"Transilvania Bridge in Satu Mare represents our long-term commitment to building future-ready infrastructure solutions for Romania," stated Herbert Schuster, Commercial Subdivision Manager at Strabag Romania. 

The bridge is designed to accommodate four traffic lanes, two pedestrian walkways, and a dedicated bicycle lane, significantly enhancing connectivity between the city's northern and southern districts.

RECOMMENDED
RECOMMENDED FROM THE HOME PAGE
Electrica secures grid permits for 700 MWh of storage
Energy

Electrica secures grid permits for 700 MWh of storage

Energy company Electrica informs investors and the capital market that it has obtained the technical grid connection permits (ATR) for 17 new battery energy storage projects (BESS), with a total capacity of approximately 700 MWh.

Energy

Romanian grid operator to support peak power consumption during heatwave

Romania's national electricity transmission network operator, Transelectrica, has halted scheduled maintenance shutdowns to ensure the grid operates at maximum capacity during an ongoing extreme heatwave. The preventive measures aim to mitigate operational risks associated with severe weather conditions.