Hidroelectrica, Siemens sign power transformer deal

Business Forum
Hidroelectrica has completed the procurement procedure for seven 216 MVA, 15.75/242 kV transformers, equipment necessary for safe operation and continued modernisation of the Porțile de Fier I Hydroelectric Power Plant.

The open tender procedure, with an estimated value of nearly €23.7 million excluding VAT, was initiated on 23 September 2025 and conducted through the Electronic Public Procurement System. Following evaluation of offers, the contract was awarded to Siemens Energy, which achieved the maximum score and submitted a financial offer worth approximately €23.4 million excluding VAT.

The acquisition is part of the company's investment programme for modernising equipment and maintaining technical performance at the Porțile de Fier I Hydroelectric Power Plant, the most important production unit in Hidroelectrica's portfolio.

"Modernising and consolidating energy infrastructure represents a strategic priority for Hidroelectrica. The acquisition of these high-power transformers for Porțile de Fier I is part of the company's constant effort to ensure installation reliability, increase operational efficiency and maintain the highest safety standards in operating vital energy facilities for the national energy system," said Bogdan Badea, CEO of Hidroelectrica.

The power plant is among Hidroelectrica's most important production units, contributing significantly to the company's total electricity generation. Located on the Danube River, the plant has an installed capacity of approximately 1,166 MW on the Romanian side, making it the largest hydroelectric plant operated by Hidroelectrica. Under normal hydrological conditions, it can produce an average of 4-5 TWh of electricity annually.

RECOMMENDED
Hidroelectrica posts 122% profit surge in Q1 2026
Energy

Hidroelectrica posts 122% profit surge in Q1 2026

Romanian energy giant Hidroelectrica recorded a net profit of €263 million in the first quarter of 2026, marking a 122% increase compared to same period last year, according to a report submitted to the BVB.

Hidroelectricas investments reach new high in 2025
Energy

Hidroelectrica's investments reach new high in 2025

State-owned power producer Hidroelectrica achieved total investments of RON 781 million (€157 million) in 2025, up 32% compared to 2024, representing the company's best investment volume in years.

Hidroelectrica reports 20% profit drop in 2025
Energy

Hidroelectrica reports 20% profit drop in 2025

State-owned power producer Hidroelectrica Group recorded a 20% fall in net profit during 2025 versus 2024 as the poor water levels significantly impacted hydropower generation and consequently the total volume of energy available for sale.

RECOMMENDED FROM THE HOME PAGE
Industry

Sphera Franchise Group posts sales growth in Q1 2026

Sphera Franchise Group, Romania's largest food service group, reported consolidated sales of €75.6 million in Q1 2026, up 4.2% compared to the same period last year. Growth was driven by the return to positive performance of KFC Romania and the strong evolution of Taco Bell.

Finance

BT posts 30% profit jump in Q1 2026

Banca Transilvania (BT) said its consolidated net profit reached RON 1.14 billion lei (€228 million) in Q1, representing a 30.1% increase compared to the same period last year. Total assets for the group expanded to RON 227 billion lei (€45.4 billion) as the institution neared the milestone of five million active customers.

Real estate

Arcadis signs major lease at Business Garden Bucharest

Vastint Romania has announced a new leasing contract with Arcadis Romania, which will occupy 1,183 sqm in building A of Business Garden Bucharest. The global design, engineering and consultancy company joins a growing community of international tenants at the development.

READ MORE
Business Forum  |  22 May, 2026 at 6:00 PM
Business Forum  |  22 May, 2026 at 1:20 PM